![]() | COMP1251 Introduction to Game Design & Development Estimated Timeline Semester 2, 2011-12 |
| Module Leader: | Oran Devilly |
| Verified by: | Dr. Hubert Shum |
| Electronic copy available: | Blackboard Learning System |
1 Project Production Milestones
Stage 1: pitch milestone
· Milestone date: 02nd Mar
· Milestone deliverables: project pitch presentation; electronic copy of project presentation.
· Indicative milestone weight: 10%
Stage 2: pre-production milestone
· Milestone date: 30th Mar
· Milestone deliverables: 1) project presentation; 2) project documentation.
· Indicative milestone weight: 10%.
Stage 3: production milestone
· Milestone date: 27th Apr
· Milestone deliverables: 1) project presentation; 2) updated project documentation; 3) project prototype, “beta” version.
· Indicative assessment weight: 30%.
Stage 4: post-production milestone
· Milestone date: 04th May
· Milestone deliverables: 1) final project documentation; 3) project prototype, “gold” version.
· Indicative milestone weight: 10%.
Students failing to attend a milestone presentation session without the module leader’s permission will receive 0% of the respective milestone mark.
Detailed requirements regarding the contents and organisation of each milestone deliverable will be provided through a brief published on the university VLE (Blackboard) in due time. You will be notified of the publication during the module sessions and via the University VLE messaging systems.
1.1 Individual learning journal
The learning journal entries will be worth 40% of the final mark.
The entries shall be delivered according to the following plan:
Journal Entry #01 – Case Study
· Submission date: 09th Mar
Journal Entry #02 – Pre-production Journal
· Submission date: 13th Apr
Journal Entry #03 – Production Journal
· Submission date: 27th Apr
Journal Entry #04 – Post-production Journal
· Submission date: 04th May
2 Submission Plan
| | Date | Project | Journal | Blackboard dropbox |
| 2011 | 03 Feb | | | |
| 10 Feb | | | | |
| 17 Feb | | | | |
| 24 Feb | | | | |
| 02 Mar | Pitch Milestone Deliverables | | Project pitch. | |
| 09 Mar | | Journal Entry #01: Case Study | Journal #01 - Case Study | |
| 16 Mar | | | | |
| 23 Mar | | | | |
| 30 Mar | Pre-production Milestone Deliverables | | Project pre-production | |
| 6 Apr | | | | |
| 16 Apr | | Journal Entry #02: Pre-production Journal | Journal #02 - Pre-production | |
| 20 Apr | | | | |
| 27 Apr | Production Milestone Deliverables | Journal Entry #03: Production Journal | Project Production / Journal #03 - Production | |
| 04 May | Post-production Milestone Deliverables | Journal Entry #04: Post-production Journal | Project Post-Production / Journal #03 - Production | |
| 11 May | | | | |
| 18 May | | | | |
| | | | |